Phase 4: Project Execution

Step 10: Construction & PMC Oversight

Physical site execution, quality control, and strict deviation management.

1. Pre-Construction Gate Checklist

Do not mobilize site teams without clearing these critical prerequisites:

CTE (Consent to Establish)Hard gate — construction legally cannot start without this in hand.
Detailed EngineeringDrawings must be formally issued "for construction", not in draft.
Fire NOCTypically tied directly to building plan approval.
Logistics & FinanceEquipment delivery schedule confirmed and loan disbursement aligned to avoid cash flow gaps.

2. Strict Construction Sequencing

Getting the sequence wrong is a common source of avoidable delays. The critical path dictates that major equipment (boilers, distillation columns) must arrive just in time for placement before walls enclose the area.

01. Site preparation & grading
02. Civil foundations pouring
03. Structural steel erection
04. Major equipment placement
05. Piping installation
06. Electrical & instrumentation
07. Insulation & painting
08. Pre-commissioning checks

3. Project Management Consultancy (PMC) Mandate

  • Schedule Management: Tracking progress against the planned sequence and flagging slippage early.
  • Quality Control: Weld checks (radiography/ultrasonic), concrete cube testing, and physical material verification against MTCs on-site. Continuation of Third-Party Inspection (TPI).
  • Contractor Coordination: Managing interfaces between civil, mechanical, piping, and electrical contractors.
  • Safety Oversight: Strict EHS compliance monitoring for high-risk pressure equipment and welding tasks.
  • Reporting: Regular updates provided to both the project owner and the lender/LIE to authorize disbursement.

4. Payment & Disbursement Milestones

Contractor payments and loan disbursements must be tied to verified physical progress, not just elapsed time:

MilestoneTypical Trigger
Mobilization AdvanceContract signing.
Civil CompletionFoundation and structural work verified complete.
Mechanical ErectionMajor equipment set and aligned.
Piping & E&I CompletionSystems ready for pre-commissioning checks.
Mechanical CompletionFull punch-list closure, ready for commissioning.
Previous: Step 09Next: Step 11 (OMC Offtake)